ONSHORE WIND · MISO

Onshore wind project J538, Hillsdale County

Onshore wind project J538, Hillsdale County is a 150 MW onshore wind request built and operating in the MISO interconnection queue, in Hillsdale County, Michigan.

Queue statusOperating
  1. PlanningQueued Nov 2015 (completed)
  2. ConsentedAug 2018 (completed)
  3. Construction (completed)
  4. OperatingOct 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J538
Grid region
MISO (Midcontinent)
Connection point (POI)
Moore Rd to Dowling 138kV line
Location
Hillsdale County, Michigan
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
GIA
Queue status
Operational
Entered queue
16 November 2015
Agreement signed
29 August 2018
Proposed online date
October 2020
Came online
October 2020

Location

Marker shows the centre of Hillsdale County; the queue data does not give exact sites.