Solar project J2314, Liberty County

Solar project J2314, Liberty County is a 150 MW solar request in interconnection study in the MISO interconnection queue, in Liberty County, Texas, connecting to ENTERGY TEXAS, INC..

Queue statusIn planning
  1. PlanningQueued Sep 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2314
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY TEXAS, INC.
Connection point (POI)
PETRY WOODS SS
Location
Liberty County, Texas
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
10 September 2021
Proposed online date
December 2023

Location

Marker shows the centre of Liberty County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Liberty County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem