SOLAR Β· MISO

Solar project J2817, Liberty County

Solar project J2817, Liberty County is a 120 MW solar request withdrawn in the MISO interconnection queue, in Liberty County, Texas, connecting to EAST TEXAS ELECTRIC COOPERATIVE, INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2817
Grid region
MISO (Midcontinent)
Utility / transmission owner
EAST TEXAS ELECTRIC COOPERATIVE, INC.
Connection point (POI)
Batiste Creek 230kV Substation
Location
Liberty County, Texas
Technology
Solar: 120 MW
Total requested
120 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
9 September 2022
Proposed online date
September 2024
Withdrawn
July 2025

Location

Marker shows the centre of Liberty County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Liberty County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem