Solar project J483, Liberty County

Solar project J483, Liberty County is a 100 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Liberty County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2015 (completed)
  2. ConsentedJul 2018 (current stage)
  3. Construction (not yet reached)
  4. OperatingSep 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J483
Grid region
MISO (Midcontinent)
Connection point (POI)
Line tap at 138 kV line approximately 6,000 ft SW of Gordon Sub
Location
Liberty County, Texas
Technology
Solar: 100 MW
Total requested
100 MW
Study phase
GIA
Queue status
Active
Entered queue
14 September 2015
Agreement signed
27 July 2018
Proposed online date
September 2020
Came online
September 2024

Location

Marker shows the centre of Liberty County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Liberty County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem