Solar project J1760, Liberty County

Solar project J1760, Liberty County is a 205 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Liberty County, Texas, connecting to ENTERGY TEXAS, INC..

Queue statusConsented
  1. PlanningQueued Jun 2020 (completed)
  2. ConsentedJan 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1760
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY TEXAS, INC.
Connection point (POI)
Timberland 230kV
Location
Liberty County, Texas
Technology
Solar: 205 MW
Total requested
205 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
15 June 2020
Agreement signed
18 January 2023
Proposed online date
June 2023

Location

Marker shows the centre of Liberty County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Liberty County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem