United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· MISO

Solar project J2767, Liberty County

Solar project J2767, Liberty County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Liberty County, Texas, connecting to ENTERGY TEXAS, INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2767
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY TEXAS, INC.
Connection point (POI)
Hightower - Rye 138kV
Location
Liberty County, Texas
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
August 2026
Withdrawn
July 2025

Location

Marker shows the centre of Liberty County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Liberty County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem