SOLAR · MISOSolar project J1096, Saline County
Solar project J1096, Saline County is a 150 MW solar request under construction in the MISO interconnection queue, in Saline County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedOct 2021 (completed)
- Construction (current stage)
- OperatingTarget Jan 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1096
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Norris City North - Muddy 138 kV Line
- Location
- Saline County, Illinois
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 12 March 2018
- Agreement signed
- 12 October 2021
- Proposed online date
- January 2024
Location
Marker shows the centre of Saline County; the queue data does not give exact sites.
Other requests in Saline County
- Solar project J1302, Saline CountySolar · 150 MW · agreement signed
- Solar project J1209, Saline CountySolar · 80.0 MW · agreement signed
- Solar project J1208, Saline CountySolar · 80.0 MW · agreement signed
- Solar project J2793, Saline CountySolar · 250 MW · in study
- Solar + storage project J3732, Saline CountySolar + storage · 175 MW · in study
- Solar + storage project J2151, Saline CountySolar + storage · 150 MW · in study
- Solar project J3916, Saline CountySolar · 100 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem