🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

SOLAR · MISO

Solar project J874, Murray County

Solar project J874, Murray County is a 150 MW solar request under construction in the MISO interconnection queue, in Murray County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.

Queue statusUnder construction
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedMay 2021 (completed)
  3. Construction (current stage)
  4. OperatingTarget Jul 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J874
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
Fenton - Chanarambie 115kV Line
Location
Murray County, Minnesota
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
16 June 2017
Agreement signed
19 May 2021
Proposed online date
July 2024

Location

Marker shows the centre of Murray County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Murray County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem