ONSHORE WIND · MISO

Onshore wind project G272, Murray County

Onshore wind project G272, Murray County is a 10.0 MW onshore wind request built and operating in the MISO interconnection queue, in Murray County, Minnesota.

Queue statusOperating
  1. PlanningQueued Dec 2002 (completed)
  2. ConsentedMay 2005 (completed)
  3. Construction (completed)
  4. OperatingSep 2004 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G272
Grid region
MISO (Midcontinent)
Connection point (POI)
Chandler Switching Station - Chandler Tap 69kV
Location
Murray County, Minnesota
Technology
Wind: 10.0 MW
Total requested
10.0 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
5 December 2002
Agreement signed
27 May 2005
Proposed online date
September 2004
Came online
September 2004

Location

Marker shows the centre of Murray County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Murray County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem