Onshore wind project J2104, Murray County

Onshore wind project J2104, Murray County is a 230 MW onshore wind request in interconnection study in the MISO interconnection queue, in Murray County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2104
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
Cedar Mountain - Lyon County 345.0kV
Location
Murray County, Minnesota
Technology
Wind: 230 MW
Total requested
230 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
17 September 2025
Proposed online date
September 2024

Location

Marker shows the centre of Murray County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Murray County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem