Onshore wind project G037, Murray County

Onshore wind project G037, Murray County is a 36.0 MW onshore wind request built and operating in the MISO interconnection queue, in Murray County, Minnesota.

Queue statusOperating
  1. PlanningQueued May 2000 (completed)
  2. ConsentedDec 2003 (completed)
  3. Construction (completed)
  4. OperatingJun 2002 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G037
Grid region
MISO (Midcontinent)
Connection point (POI)
Chanarambie Substation
Location
Murray County, Minnesota
Technology
Wind: 36.0 MW
Total requested
36.0 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
12 May 2000
Agreement signed
2 December 2003
Proposed online date
June 2002
Came online
June 2002

Location

Marker shows the centre of Murray County; the queue data does not give exact sites.