United States › Grid › Interconnection queues › Minnesota
ONSHORE WIND · MISOOnshore wind project G492, Murray County
Onshore wind project G492, Murray County is a 5.0 MW onshore wind request built and operating in the MISO interconnection queue, in Murray County, Minnesota.
Request details
- Queue ID
- G492
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Southridge Substation - SRD 211
- Location
- Murray County, Minnesota
- Technology
- Wind: 5.0 MW
- Total requested
- 5.0 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 4 February 2005
- Agreement signed
- 6 June 2005
- Proposed online date
- December 2005
- Came online
- December 2005
Location
Marker shows the centre of Murray County; the queue data does not give exact sites.
Other requests in Murray County
- Solar project J874, Murray CountySolar · 150 MW · under construction
- Battery storage project J1045, Murray CountyBattery storage · 20.0 MW · under construction
- Onshore wind project J2104, Murray CountyOnshore wind · 230 MW · in study
- Onshore wind project J2447, Murray CountyOnshore wind · 200 MW · in study
- Onshore wind project J2346, Murray CountyOnshore wind · 200 MW · in study
- Solar project J2309, Murray CountySolar · 100 MW · in study
- Onshore wind project G060, Murray CountyOnshore wind · 100 MW · built
- Onshore wind project G057, Murray CountyOnshore wind · 80.0 MW · built
- Onshore wind project G037, Murray CountyOnshore wind · 36.0 MW · built
- Onshore wind project G272, Murray CountyOnshore wind · 10.0 MW · built
- Onshore wind project G252, Murray CountyOnshore wind · 10.0 MW · built
- Onshore wind project G851, Murray CountyOnshore wind · 250 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem