Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 61 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project G0363, Gilliam County
Onshore wind
204 MWIn study Gilliam, ORWest Apr 2009target 2012
Corazon Solar Phase II
Solar + storage · BAYWA R.E. SOLAR PROJECTS
204 MWAgreement signed Webb, TXERCOT Dec 2019target 2028
Sowers Storage
Battery storage · Sowers Energy Storage LLC
204 MWAgreement signed Kaufman, TXERCOT Aug 2021target 2026
Stockdale BESS
Battery storage
204 MWPaused / redesign Wilson, TXERCOT Mar 2022
Utica BESS
Battery storage
204 MWPaused / redesign Guadalupe, TXERCOT Sep 2022
Soda Lake BESS 1
Battery storage · Mendoza Trail BESS, LLC
204 MWAgreement signed Crane, TXERCOT Sep 2022target 2026
Huaso Hybrid
Solar + storage
204 MWAgreement signed Fresno, CACAISO Apr 2021target 2026
Battery Storage
Battery storage
204 MWAgreement signed Worcester, MAISO-NE Oct 2022target 2027
Chimney Creek Solar
Solar · Chimney Creek Energy, LLC
204 MWIn study Shackelford, TXERCOT Feb 2025target 2030
Pumpkin Patch
Solar · Hoosier Energy
204 MWIn study Greene, ILMISO Nov 2025target 2028
Cornwall BESS
Battery storage
204 MWPaused / redesign Williamson, TXERCOT Mar 2022
Sierra Diablo Energy Storage
Battery storage · SIERRA DIABLO ENERGY STORAGE LLC
204 MWIn study Van Zandt, TXERCOT Aug 2022target 2026
Sultan BESS
Battery storage
204 MWPaused / redesign Bosque, TXERCOT Mar 2022
Black & Gold Energy Storage
Battery storage · Black & Gold Energy Storage, LLC
204 MWAgreement signed Menard, TXERCOT Jul 2022target 2027
Diamondback solar
Solar · Diamondback Solar, LLC
204 MWAgreement signed Starr, TXERCOT Sep 2018target 2027
Ringtail Energy Storage
Battery storage · PowerPulse LLC
204 MWIn study Archer, TXERCOT Apr 2025target 2028
Diamondback BESS
Battery storage
204 MWPaused / redesign Starr, TXERCOT Mar 2022
Puma Storage
Battery storage
204 MWIn study Madera, CACAISO Apr 2021target 2030
Seahawk Storage
Battery storage
204 MWAgreement signed Santa Cruz, CACAISO Apr 2021target 2029
Cougar Storage
Battery storage
204 MWAgreement signed Merced, CACAISO Apr 2021target 2030
Apache Storage
Battery storage
204 MWAgreement signed Fresno, CACAISO Apr 2021target 2029
Kingsroad Hybrid Solar
Solar + storage
204 MWAgreement signed Kern, CACAISO Apr 2019target 2028
Puff Hybrid Solar
Solar + storage
204 MWIn study Kern, CACAISO Apr 2020target 2030
Barton Branch IA
Battery storage · Barton Branch IA LLC
204 MWAgreement signed Robertson, TXERCOT Mar 2021target 2026
Tidwell Prairie II Batt
Battery storage · TIDWELL PRAIRIE II LLC
204 MWAgreement signed Robertson, TXERCOT Mar 2021target 2026
Mercury Solar III
Solar + storage · Mercury Solar
204 MWIn study Hill, TXERCOT Aug 2022target 2029
Fewell Solar
Solar · Fewell Solar LLC
204 MWAgreement signed Limestone, TXERCOT Aug 2021target 2027
Owens Solar
Solar · Owens Solar LLC
204 MWPaused / redesign Bosque, TXERCOT Feb 2022target 2025
Glasgow Solar
Solar + storage · Glasgow Solar LLC
204 MWAgreement signed Navarro, TXERCOT Feb 2022target 2027
Timberlakes Solar
Solar · Donegalsol
204 MWIn study Dickens, TXERCOT Nov 2022target 2026
Solar project GEN-2018-057, Sedgwick County
Solar
203 MWAgreement signed Sedgwick, KSSPP May 2018target 2030
Nockenut Springs Solar 2
Solar · Pecan Springs Energy, LLC
203 MWAgreement signed Guadalupe, TXERCOT Sep 2020target 2029
Nockenut Springs Solar 1
Solar · Pecan Springs Energy, LLC
203 MWAgreement signed Guadalupe, TXERCOT Sep 2020target 2029
Marcelina Storage
Battery storage · Marcelina Solar, LLC
203 MWIn study Wilson, TXERCOT Aug 2021target 2026
Callisto II Energy Center
Battery storage · Callisto II Energy Center LLC
203 MWAgreement signed Harris, TXERCOT Oct 2021target 2026
Brookview Road BESS
Battery storage · Brookview Reliability Project LLC
203 MWAgreement signed Harris, TXERCOT Apr 2024target 2028
Kinenos Solar
Solar · Encino del Sol Energy, LLC
203 MWIn study Brooks, TXERCOT Dec 2020target 2026
Loma Pinta Solar
Solar · Loma Pinta Wind Energy, LLC
203 MWIn study La Salle, TXERCOT Jun 2020target 2027
Brahman Renewables Storage
Solar + storage · Brahman Renewables
203 MWIn study Milam, TXERCOT Oct 2024target 2029
Big Star Solar
Solar · RWE Solar Development, LLC
203 MWAgreement signed Bastrop, TXERCOT Aug 2019target 2026
OCI Cobb Creek Solar
Solar + storage · Hillsboro Solar Project LLC
203 MWAgreement signed Hill, TXERCOT Nov 2022target 2027
Little Bear 4
Solar + storage
203 MWAgreement signed Fresno, CACAISO Apr 20152020
Caracara Energy Storage Center
Battery storage · FRESH AIR ENERGY II, LLC
203 MWIn study Bexar, TXERCOT May 2024target 2028
Onshore wind project GEN-2021-025, Woodward County
Onshore wind
203 MWIn study Woodward, OKSPP May 2021target 2026
Bigway Solar I
Solar · NextEra Energy Interconnection Holdings, LLC
203 MWAgreement signed King, TXERCOT Jan 2024target 2028
Charro Creek Solar 1 SLF
Solar + storage · Charro Creek Solar LLC
203 MWIn study Karnes, TXERCOT Jan 2023target 2026
Bigway Solar II
Solar · NextEra Energy Interconnection Holdings, LLC
203 MWAgreement signed King, TXERCOT Dec 2023target 2028
Nazareth Solar
Solar · TX Nazareth Solar, LLC
203 MWAgreement signed Castro, TXERCOT Jun 2014target 2027
Washington County Solar
Solar + storage
203 MWIn study Washington, GASoutheast Oct 2024target 2027
Samson Solar 2
Solar · Samson Solar Energy II LLC
203 MWAgreement signed Lamar, TXERCOT Jan 2020target 2026
Page 61 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)