United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTChimney Creek Solar
Chimney Creek Solar is a 204 MW solar request in interconnection study in the ERCOT interconnection queue, in Shackelford County, Texas.
Queue statusIn planning
- PlanningQueued Feb 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0151
- Grid region
- ERCOT (Texas)
- Developer
- Chimney Creek Energy, LLC
- Connection point (POI)
- Tap 345 kV 68000 West Shackelford – 60515 Clear Crossing Ckt 1
- Location
- Shackelford County, Texas
- Technology
- Solar: 204 MW
- Total requested
- 204 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 14 February 2025
- Proposed online date
- May 2030
Location
Marker shows the centre of Shackelford County; the queue data does not give exact sites.
Other requests in Shackelford County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem