United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Tidwell Prairie II Batt

Tidwell Prairie II Batt is a 204 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Robertson County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2021 (completed)
  2. ConsentedJan 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0503
Grid region
ERCOT (Texas)
Developer
TIDWELL PRAIRIE II LLC
Connection point (POI)
Tap 345kV 3400 Twin Oak - 39950 TNP One
Location
Robertson County, Texas
Technology
Battery: 204 MW
Total requested
204 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
16 March 2021
Agreement signed
13 January 2025
Proposed online date
June 2026

Location

Marker shows the centre of Robertson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Robertson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem