SOLAR · ERCOT

Kinenos Solar

Kinenos Solar is a 203 MW solar request in interconnection study in the ERCOT interconnection queue, in Brooks County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0087
Grid region
ERCOT (Texas)
Developer
Encino del Sol Energy, LLC
Connection point (POI)
tap 345kV 8905 North Edinburg - 8455 Lon Hill
Location
Brooks County, Texas
Technology
Solar: 203 MW
Total requested
203 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 December 2020
Proposed online date
December 2026

Location

Marker shows the centre of Brooks County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brooks County