🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Falfur BESS

Falfur BESS is a 9.8 MW battery storage request built and operating in the ERCOT interconnection queue, in Brooks County, Texas.

Queue statusOperating
  1. PlanningQueued Jun 2023 (completed)
  2. ConsentedJun 2024 (completed)
  3. Construction (completed)
  4. OperatingFeb 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0593
Grid region
ERCOT (Texas)
Developer
Regis Falfurrias, LLC
Connection point (POI)
Connected to AEP 12.47kV Station Name (TDSP Station Code): FALFUR Load/Load Transformer Name: R1 PTI Bus Number: #8510 Voltage in kV (Transmission Level): 138kV
Location
Brooks County, Texas
Technology
Battery: 9.8 MW
Total requested
9.8 MW
Study phase
MRD Approved
Queue status
Operational
Entered queue
27 June 2023
Agreement signed
21 June 2024
Proposed online date
August 2025
Came online
February 2025

Location

Marker shows the centre of Brooks County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brooks County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem