United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTSowers Storage
Sowers Storage is a 204 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Kaufman County, Texas.
Queue statusConsented
- PlanningQueued Aug 2021 (completed)
- ConsentedApr 2022 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 22INR0552
- Grid region
- ERCOT (Texas)
- Developer
- Sowers Energy Storage LLC
- Connection point (POI)
- 6894 Rose Hill_RC Sub 138 kV
- Location
- Kaufman County, Texas
- Technology
- Battery: 204 MW
- Total requested
- 204 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 18 August 2021
- Agreement signed
- 22 April 2022
- Proposed online date
- December 2026
Location
Marker shows the centre of Kaufman County; the queue data does not give exact sites.
Other requests in Kaufman County
- Mystic Springs Renewable Energy Solar SLFSolar + storage · 259 MW · agreement signed
- Erika SolarSolar + storage · 201 MW · agreement signed
- Eliza SolarSolar · 152 MW · agreement signed
- Lubio SolarSolar · 54.5 MW · agreement signed
- Solarville Solar SLFSolar + storage · 403 MW · in study
- Yellow Leaf II BESSSolar + storage · 206 MW · in study
- Yellow Leaf SolarSolar + storage · 105 MW · in study
- Fudge Ranch BESSBattery storage · 104 MW · in study
- Yellow Leaf BESSSolar + storage · 104 MW · in study
- Erika BESSSolar + storage · 100 MW · in study
- Sunbelt SolarSolar + storage · 81.5 MW · in study
- Sunbelt StorageSolar + storage · 52.0 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem