United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Lubio Solar

Lubio Solar is a 54.5 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Kaufman County, Texas.

Queue statusConsented
  1. PlanningQueued Oct 2020 (completed)
  2. ConsentedNov 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0426
Grid region
ERCOT (Texas)
Developer
BDPU Solar Lubio LLC
Connection point (POI)
tap 138kV 2727 Crandall - 2724 Kaufman Northwest
Location
Kaufman County, Texas
Technology
Solar: 54.5 MW
Total requested
54.5 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
7 October 2020
Agreement signed
8 November 2024
Proposed online date
April 2028

Location

Marker shows the centre of Kaufman County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Kaufman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem