United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTMystic Springs Renewable Energy Solar SLF
Mystic Springs Renewable Energy Solar SLF is a 259 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Kaufman County, Texas.
Queue statusConsented
- PlanningQueued May 2022 (completed)
- ConsentedOct 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 24INR0339
- Grid region
- ERCOT (Texas)
- Developer
- Mystic Spring Renewable Energy LLC
- Connection point (POI)
- Tap 345 kV Royse Switch (2478) – Poetry Switch (2485)
- Location
- Kaufman County, Texas
- Technology
- Solar: 259 MW · Battery
- Total requested
- 259 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 10 May 2022
- Agreement signed
- 30 October 2025
- Proposed online date
- March 2028
Location
Marker shows the centre of Kaufman County; the queue data does not give exact sites.
Other requests in Kaufman County
- Sowers StorageBattery storage · 204 MW · agreement signed
- Erika SolarSolar + storage · 201 MW · agreement signed
- Eliza SolarSolar · 152 MW · agreement signed
- Lubio SolarSolar · 54.5 MW · agreement signed
- Solarville Solar SLFSolar + storage · 403 MW · in study
- Yellow Leaf II BESSSolar + storage · 206 MW · in study
- Yellow Leaf SolarSolar + storage · 105 MW · in study
- Fudge Ranch BESSBattery storage · 104 MW · in study
- Yellow Leaf BESSSolar + storage · 104 MW · in study
- Erika BESSSolar + storage · 100 MW · in study
- Sunbelt SolarSolar + storage · 81.5 MW · in study
- Sunbelt StorageSolar + storage · 52.0 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem