SOLAR + STORAGE · ERCOT

Mystic Springs Renewable Energy Solar SLF

Mystic Springs Renewable Energy Solar SLF is a 259 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Kaufman County, Texas.

Queue statusConsented
  1. PlanningQueued May 2022 (completed)
  2. ConsentedOct 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0339
Grid region
ERCOT (Texas)
Developer
Mystic Spring Renewable Energy LLC
Connection point (POI)
Tap 345 kV Royse Switch (2478) – Poetry Switch (2485)
Location
Kaufman County, Texas
Technology
Solar: 259 MW · Battery
Total requested
259 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
10 May 2022
Agreement signed
30 October 2025
Proposed online date
March 2028

Location

Marker shows the centre of Kaufman County; the queue data does not give exact sites.