United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Yellow Leaf II BESS

Yellow Leaf II BESS is a 206 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Kaufman County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0412
Grid region
ERCOT (Texas)
Developer
Yellow Leaf 2 BESS LLC
Connection point (POI)
Tap 138kV 2727 CRANDALL1_8 - 2724 KAUFMN_8
Location
Kaufman County, Texas
Technology
Battery: 206 MW · Battery
Total requested
206 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 July 2025
Proposed online date
September 2028

Location

Marker shows the centre of Kaufman County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Kaufman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem