SOLAR · MISOPumpkin Patch
Pumpkin Patch is a 204 MW solar request in interconnection study in the MISO interconnection queue, in Greene County, Illinois, connecting to Hoosier Energy.
Queue statusIn planning
- PlanningQueued Nov 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- E0052
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Hoosier Energy
- Developer
- Hoosier Energy
- Connection point (POI)
- Roadhouse West Substation
- Location
- Greene County, Illinois
- Technology
- Solar: 204 MW
- Total requested
- 204 MW
- Service type
- Network resource (NRIS)
- Study phase
- Request Status: Active; Post GIA Status: Not started
- Queue status
- Active
- Entered queue
- 6 November 2025
- Proposed online date
- December 2028
Location
Marker shows the centre of Greene County; the queue data does not give exact sites.
Other requests in Greene County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem