United States › Grid › Interconnection queues › Illinois

SOLAR · MISO

Solar project J644, Greene County

Solar project J644, Greene County is a 110 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Greene County, Illinois.

Queue statusConsented
  1. PlanningQueued May 2016 (completed)
  2. ConsentedOct 2018 (current stage)
  3. Construction (not yet reached)
  4. OperatingNov 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J644
Grid region
MISO (Midcontinent)
Connection point (POI)
Jerseyville 138kV
Location
Greene County, Illinois
Technology
Solar: 110 MW
Total requested
110 MW
Study phase
GIA
Queue status
Active
Entered queue
9 May 2016
Agreement signed
30 October 2018
Proposed online date
December 2020
Came online
November 2024

Location

Marker shows the centre of Greene County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Greene County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem