🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Ringtail Energy Storage

Ringtail Energy Storage is a 204 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Archer County, Texas.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0348
Grid region
ERCOT (Texas)
Developer
PowerPulse LLC
Connection point (POI)
Bus # 1446, Lake Wichita, 138 kV
Location
Archer County, Texas
Technology
Battery: 204 MW
Total requested
204 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
25 April 2025
Proposed online date
December 2028

Location

Marker shows the centre of Archer County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Archer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem