United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Red Hollow Renewable Energy Solar SLF

Red Hollow Renewable Energy Solar SLF is a 309 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Archer County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0088
Grid region
ERCOT (Texas)
Developer
Red Hollow Renewable Energy LLC
Connection point (POI)
Tap 345kV (Bus# 1422) Bowman - (Bus# 17002) Garvey Road
Location
Archer County, Texas
Technology
Solar: 309 MW · Battery
Total requested
309 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
1 July 2024
Proposed online date
April 2028

Location

Marker shows the centre of Archer County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Archer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem