United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTHat Creek Solar
Hat Creek Solar is a 252 MW solar request withdrawn in the ERCOT interconnection queue, in Archer County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedFeb 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 21INR0293
- Grid region
- ERCOT (Texas)
- Developer
- Hat Creek Solar, LLC
- Connection point (POI)
- 1464 South Wichita Falls 138kV
- Location
- Archer County, Texas
- Technology
- Solar: 252 MW
- Total requested
- 252 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 17 April 2019
- Proposed online date
- June 2022
- Withdrawn
- February 2022
Location
Marker shows the centre of Archer County; the queue data does not give exact sites.
Other requests in Archer County
- Red Hollow Renewable Energy Solar SLFSolar + storage Β· 309 MW Β· in study
- Ringtail Energy StorageBattery storage Β· 204 MW Β· in study
- Carolina Storage Wichita FallsBattery storage Β· 202 MW Β· in study
- Berryman Road StorageBattery storage Β· 155 MW Β· in study
- Trinity Hills BESS SLFBattery storage Β· 94.0 MW Β· in study
- Shannon Wind RepowerOnshore wind Β· 18.5 MW Β· in study
- Bobcat Bluff repowerOnshore wind Β· 12.0 MW Β· built
- Jaguarundi StorageOther Β· 91.1 MW Β· withdrawn
- Jaguarundi SolarSolar Β· 90.3 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem