BATTERY STORAGE · ERCOT

Trinity Hills BESS SLF

Trinity Hills BESS SLF is a 94.0 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Archer County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0295
Grid region
ERCOT (Texas)
Developer
Phoenix Battery Storage, LLC
Connection point (POI)
To the 345 kV Garvey Road Switch (#17002)
Location
Archer County, Texas
Technology
Battery: 94.0 MW
Total requested
94.0 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
30 November 2023
Proposed online date
April 2027

Location

Marker shows the centre of Archer County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Archer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem