United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTFewell Solar
Fewell Solar is a 204 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Limestone County, Texas.
Queue statusConsented
- PlanningQueued Aug 2021 (completed)
- ConsentedAug 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0367
- Grid region
- ERCOT (Texas)
- Developer
- Fewell Solar LLC
- Connection point (POI)
- Tap 138kV 3597 Groesbeck - 3634 Groesbeck Main
- Location
- Limestone County, Texas
- Technology
- Solar: 204 MW
- Total requested
- 204 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 19 August 2021
- Agreement signed
- 18 August 2023
- Proposed online date
- March 2027
Location
Marker shows the centre of Limestone County; the queue data does not give exact sites.
Other requests in Limestone County
- Diver SolarSolar · 226 MW · agreement signed
- Leighton Solar SLFSolar · 183 MW · agreement signed
- Bonham Solar SLFSolar + storage · 138 MW · agreement signed
- Varadero SolarSolar · 206 MW · in study
- Bonham Storage SLFSolar + storage · 105 MW · in study
- Naduah SolarSolar · 77.6 MW · in study
- Findley BESSSolar + storage · 51.7 MW · in study
- Findley SolarSolar + storage · 50.3 MW · in study
- Chariot StorageBattery storage · 50.0 MW · in study
- Tehuacana WindOnshore wind · 600 MW · suspended
- Fiji SolarSolar · 203 MW · suspended
- MexiAltaSolar · 180 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem