United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Bonham Solar SLF

Bonham Solar SLF is a 138 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Limestone County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2022 (completed)
  2. ConsentedAug 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0199
Grid region
ERCOT (Texas)
Developer
J&J Solar Ranch LLC
Connection point (POI)
TAP 138 kV MEXIA_2_1_8 3632 - GROES_SE1_8 3634
Location
Limestone County, Texas
Technology
Solar: 138 MW · Battery
Total requested
138 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
15 November 2022
Agreement signed
7 August 2024
Proposed online date
April 2027

Location

Marker shows the centre of Limestone County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Limestone County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem