United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTMexiAlta
MexiAlta is a 180 MW solar request withdrawn in the ERCOT interconnection queue, in Limestone County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2021 (completed)
- Withdrawn / abandonedJun 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 23INR0294
- Grid region
- ERCOT (Texas)
- Developer
- Greenfields Solar LLC
- Connection point (POI)
- Tap 138kV 3632 Mexia - 3634 Groesbeck
- Location
- Limestone County, Texas
- Technology
- Solar: 180 MW
- Total requested
- 180 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Entered queue
- 8 June 2021
- Proposed online date
- June 2023
- Withdrawn
- June 2021
Location
Marker shows the centre of Limestone County; the queue data does not give exact sites.
Other requests in Limestone County
- Diver SolarSolar Β· 226 MW Β· agreement signed
- Fewell SolarSolar Β· 204 MW Β· agreement signed
- Leighton Solar SLFSolar Β· 183 MW Β· agreement signed
- Bonham Solar SLFSolar + storage Β· 138 MW Β· agreement signed
- Varadero SolarSolar Β· 206 MW Β· in study
- Bonham Storage SLFSolar + storage Β· 105 MW Β· in study
- Naduah SolarSolar Β· 77.6 MW Β· in study
- Findley BESSSolar + storage Β· 51.7 MW Β· in study
- Findley SolarSolar + storage Β· 50.3 MW Β· in study
- Chariot StorageBattery storage Β· 50.0 MW Β· in study
- Tehuacana WindOnshore wind Β· 600 MW Β· suspended
- Fiji SolarSolar Β· 203 MW Β· suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem