United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTChariot Storage
Chariot Storage is a 50.0 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Limestone County, Texas.
Queue statusIn planning
- PlanningQueued Mar 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 21INR0260
- Grid region
- ERCOT (Texas)
- Developer
- Chariot Storage LLC
- Connection point (POI)
- tap 69kV 99 Ben Hur - 107 Prairie Hill
- Location
- Limestone County, Texas
- Technology
- Battery: 50.0 MW
- Total requested
- 50.0 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 6 March 2019
- Proposed online date
- February 2028
Location
Marker shows the centre of Limestone County; the queue data does not give exact sites.
Other requests in Limestone County
- Diver SolarSolar · 226 MW · agreement signed
- Fewell SolarSolar · 204 MW · agreement signed
- Leighton Solar SLFSolar · 183 MW · agreement signed
- Bonham Solar SLFSolar + storage · 138 MW · agreement signed
- Varadero SolarSolar · 206 MW · in study
- Bonham Storage SLFSolar + storage · 105 MW · in study
- Naduah SolarSolar · 77.6 MW · in study
- Findley BESSSolar + storage · 51.7 MW · in study
- Findley SolarSolar + storage · 50.3 MW · in study
- Tehuacana WindOnshore wind · 600 MW · suspended
- Fiji SolarSolar · 203 MW · suspended
- MexiAltaSolar · 180 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem