SOLAR · ERCOTLeighton Solar SLF
Leighton Solar SLF is a 183 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Limestone County, Texas.
Queue statusConsented
- PlanningQueued May 2022 (completed)
- ConsentedMay 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 24INR0298
- Grid region
- ERCOT (Texas)
- Developer
- Lavender Solar LLC
- Connection point (POI)
- 99 BENHUR 69kV
- Location
- Limestone County, Texas
- Technology
- Solar: 183 MW
- Total requested
- 183 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 11 May 2022
- Agreement signed
- 28 May 2024
- Proposed online date
- September 2027
Location
Marker shows the centre of Limestone County; the queue data does not give exact sites.
Other requests in Limestone County
- Diver SolarSolar · 226 MW · agreement signed
- Fewell SolarSolar · 204 MW · agreement signed
- Bonham Solar SLFSolar + storage · 138 MW · agreement signed
- Varadero SolarSolar · 206 MW · in study
- Bonham Storage SLFSolar + storage · 105 MW · in study
- Naduah SolarSolar · 77.6 MW · in study
- Findley BESSSolar + storage · 51.7 MW · in study
- Findley SolarSolar + storage · 50.3 MW · in study
- Chariot StorageBattery storage · 50.0 MW · in study
- Tehuacana WindOnshore wind · 600 MW · suspended
- Fiji SolarSolar · 203 MW · suspended
- MexiAltaSolar · 180 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem