Callisto II Energy Center

Callisto II Energy Center is a 203 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Harris County, Texas.

Queue statusConsented
  1. PlanningQueued Oct 2021 (completed)
  2. ConsentedDec 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0558
Grid region
ERCOT (Texas)
Developer
Callisto II Energy Center LLC
Connection point (POI)
47150 HO Clarke 138kV
Location
Harris County, Texas
Technology
Battery: 203 MW
Total requested
203 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
7 October 2021
Agreement signed
11 December 2023
Proposed online date
July 2026

Location

Marker shows the centre of Harris County; the queue data does not give exact sites.