United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTMegamouth Energy Storage
Megamouth Energy Storage is a 101 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Harris County, Texas.
Queue statusConsented
- PlanningQueued Mar 2024 (completed)
- ConsentedNov 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 26INR0341
- Grid region
- ERCOT (Texas)
- Developer
- GCI Megamouth, LLC
- Connection point (POI)
- 42750 Mykawa 138 kV
- Location
- Harris County, Texas
- Technology
- Battery: 101 MW
- Total requested
- 101 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 22 March 2024
- Agreement signed
- 18 November 2025
- Proposed online date
- December 2028
Location
Marker shows the centre of Harris County; the queue data does not give exact sites.
Other requests in Harris County
- Elmax Power StationGas · 519 MW · agreement signed
- NRG THW GT 345 (Tef)Gas · 456 MW · agreement signed
- NRG Greens Bayou 6 (TEF-Due Diligence)Gas · 445 MW · agreement signed
- Rhapsody StorageBattery storage · 206 MW · agreement signed
- Callisto II Energy CenterBattery storage · 203 MW · agreement signed
- Brookview Road BESSBattery storage · 203 MW · agreement signed
- Houston IV BESSBattery storage · 165 MW · agreement signed
- Dori BQ BESSSolar + storage · 154 MW · agreement signed
- Friendswood Energy GencoGas · 144 MW · agreement signed
- Remy Jade III Power StationGas · 102 MW · agreement signed
- Pamela Heights IBattery storage · 102 MW · agreement signed
- Dori BQ SolarSolar + storage · 50.4 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem