United States › Grid › Interconnection queues › Texas
GAS · ERCOTFriendswood Energy Genco
Friendswood Energy Genco is a 144 MW gas request with a signed interconnection agreement in the ERCOT interconnection queue, in Harris County, Texas.
Queue statusConsented
- PlanningQueued Dec 2022 (completed)
- ConsentedApr 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 24INR0456
- Grid region
- ERCOT (Texas)
- Developer
- Tejas Power Generation LLC
- Connection point (POI)
- 47170 H O CLARKE 138KV
- Location
- Harris County, Texas
- Technology
- Gas: 144 MW
- Total requested
- 144 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 7 December 2022
- Agreement signed
- 23 April 2024
- Proposed online date
- February 2026
Location
Marker shows the centre of Harris County; the queue data does not give exact sites.
Other requests in Harris County
- Elmax Power StationGas · 519 MW · agreement signed
- NRG THW GT 345 (Tef)Gas · 456 MW · agreement signed
- NRG Greens Bayou 6 (TEF-Due Diligence)Gas · 445 MW · agreement signed
- Rhapsody StorageBattery storage · 206 MW · agreement signed
- Callisto II Energy CenterBattery storage · 203 MW · agreement signed
- Brookview Road BESSBattery storage · 203 MW · agreement signed
- Houston IV BESSBattery storage · 165 MW · agreement signed
- Dori BQ BESSSolar + storage · 154 MW · agreement signed
- Remy Jade III Power StationGas · 102 MW · agreement signed
- Pamela Heights IBattery storage · 102 MW · agreement signed
- Megamouth Energy StorageBattery storage · 101 MW · agreement signed
- Dori BQ SolarSolar + storage · 50.4 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem