United States › Grid › Interconnection queues › Texas

GAS · ERCOT

NRG Greens Bayou 6 (TEF-Due Diligence)

NRG Greens Bayou 6 (TEF-Due Diligence) is a 445 MW gas request with a signed interconnection agreement in the ERCOT interconnection queue, in Harris County, Texas.

Queue statusConsented
  1. PlanningQueued Aug 2022 (completed)
  2. ConsentedFeb 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0410
Grid region
ERCOT (Texas)
Developer
NRG Greens Bayou 6 LLC
Connection point (POI)
Position 1/0 PSSE 40710, Greens Bayou Substation, 138 kV
Location
Harris County, Texas
Technology
Gas: 445 MW
Total requested
445 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
16 August 2022
Agreement signed
7 February 2025
Proposed online date
May 2028

Location

Marker shows the centre of Harris County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Harris County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem