BATTERY STORAGE · ERCOT

Pamela Heights I

Pamela Heights I is a 102 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Harris County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2024 (completed)
  2. ConsentedOct 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
28INR0154
Grid region
ERCOT (Texas)
Developer
Pamela heights I Energy Center LLC
Connection point (POI)
#47150 HOC 138kV
Location
Harris County, Texas
Technology
Battery: 102 MW
Total requested
102 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
10 September 2024
Agreement signed
7 October 2025
Proposed online date
July 2026

Location

Marker shows the centre of Harris County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Harris County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem