United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTDiamondback solar
Diamondback solar is a 204 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Starr County, Texas.
Queue statusConsented
- PlanningQueued Sep 2018 (completed)
- ConsentedJun 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 20INR0162
- Grid region
- ERCOT (Texas)
- Developer
- Diamondback Solar, LLC
- Connection point (POI)
- 80355 Del Sol 345kV
- Location
- Starr County, Texas
- Technology
- Solar: 204 MW
- Total requested
- 204 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 13 September 2018
- Agreement signed
- 14 June 2024
- Proposed online date
- December 2027
Location
Marker shows the centre of Starr County; the queue data does not give exact sites.
Other requests in Starr County
- Half Moon SolarSolar · 513 MW · agreement signed
- Bullring Wind 2Onshore wind · 304 MW · agreement signed
- Bullring Wind 1Onshore wind · 304 MW · agreement signed
- Mesteno WindOnshore wind · 202 MW · agreement signed
- Bullring Wind 3Onshore wind · 190 MW · agreement signed
- Starr Solar RanchSolar + storage · 137 MW · agreement signed
- Fierce River SolarSolar + storage · 896 MW · in study
- Muy Grande SolarSolar · 503 MW · in study
- Mandolin Solar SLFSolar + storage · 300 MW · in study
- Fierce River BESSSolar + storage · 285 MW · in study
- Bessie StorageBattery storage · 211 MW · in study
- PSE Gongora Hill TX StorageBattery storage · 200 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem