United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTBlack & Gold Energy Storage
Black & Gold Energy Storage is a 204 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Menard County, Texas.
Queue statusConsented
- PlanningQueued Jul 2022 (completed)
- ConsentedAug 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 24INR0386
- Grid region
- ERCOT (Texas)
- Developer
- Black & Gold Energy Storage, LLC
- Connection point (POI)
- 6364 Yellow Jacket Sub 138kV
- Location
- Menard County, Texas
- Technology
- Battery: 204 MW
- Total requested
- 204 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 18 July 2022
- Agreement signed
- 14 August 2024
- Proposed online date
- July 2027
Location
Marker shows the centre of Menard County; the queue data does not give exact sites.
Other requests in Menard County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem