United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA — page 139
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project AI2-216, Pulaski County Onshore wind |
77.0 MW | In study |
| Onshore wind project AH2-292, Cambria County Onshore wind |
77.0 MW | In study |
| Gas project Q31, Maricopa County Gas |
77.0 MW | In study |
| Solar + storage project J3630, East Feliciana Parish County Solar + storage |
77.0 MW | In study |
| Knox County Moore Storage Battery storage · DM-KCM, LLC |
77.0 MW | In study |
| Lytton Springs BESS Solar + storage · SMT Lytton Springs LLC |
76.4 MW | In study |
| Eytcheson Ranches Solar Solar · Gransolar Texas Fourteen, LLC |
76.4 MW | In study |
| Serengeti Solar Solar · Abei Energy Green XIV LLC |
76.2 MW | In study |
| Montezuma (High Winds III) Wind + storage |
76.0 MW | Agreement signed |
| Gas project 417, Volusia County Gas · FPL |
76.0 MW | In study |
| Iris Del Sol Solar + storage |
76.0 MW | Agreement signed |
| Solar project G0517, Morrow County Solar |
76.0 MW | In study |
| Myers Storage Solar + storage · BT Myers Solar, LLC |
76.0 MW | In study |
| Gas project 20230829006, Jasper County Gas · DESC - Generation |
76.0 MW | In study |
| Solar project 568892, Darlington County Solar · Duke Energy Progress, LLC |
76.0 MW | Agreement signed |
| Palmetto Energy Storage Battery storage |
75.6 MW | In study |
| Donelson Solar SLF Solar + storage · Donelson Solar |
75.4 MW | In study |
| PaleAle BESS Battery storage · Momentum Energy Storage Partners,LLC |
75.4 MW | In study |
| Lytton Springs Solar Solar + storage · SMT Lytton Springs LLC |
75.3 MW | In study |
| Battery storage project G0717, Klickitat County Battery storage |
75.0 MW | In study |
| Scarboro Solar Solar + storage |
75.0 MW | In study |
| Battery storage project GEN-2024-310, Chaves County Battery storage |
75.0 MW | In study |
| Battery storage project AI2-040, Orange County Battery storage |
75.0 MW | In study |
| Solar project 565080, Darlington County Solar |
75.0 MW | Agreement signed |
| Battery storage project J1411, Dane County Battery storage |
75.0 MW | Agreement signed |
| Battery storage project Q611, Maricopa County Battery storage |
75.0 MW | In study |
| Onshore wind project GI-2025-05, Logan County Onshore wind |
75.0 MW | In study |
| Battery storage project AI2-041, Halifax County Battery storage |
75.0 MW | In study |
| Battery storage project GEN-2021-052, Muskogee County Battery storage |
75.0 MW | Agreement signed |
| East Blackland Battery Storage SLF Solar + storage · DERIVA ENERGY STORAGE, LLC |
75.0 MW | In study |
| Macadamia Solar Solar |
75.0 MW | Agreement signed |
| Battery storage project S0018, Tooele County Battery storage |
75.0 MW | In study |
| Solar project 167, Darlington County Solar |
75.0 MW | Paused / redesign |
| Gas project J2948, Marshall County Gas |
75.0 MW | In study |
| Solar project 20220112001, Hampton County Solar · Greenbow Solar Park LLC |
75.0 MW | In study |
| Battery storage project 1RSC-2020-02, Pueblo County Battery storage |
75.0 MW | Agreement signed |
| Daphne Energy Storage Battery storage · Hanwha Q CELLS USA Corp. |
75.0 MW | In study |
| Battery storage project AH2-227, Jay County Battery storage |
75.0 MW | In study |
| Onshore wind project GI-2006-1h, Prowers County Onshore wind |
75.0 MW | Agreement signed |
| Solar project 238, Marion County Solar |
75.0 MW | In study |
| Hummingbird Energy Storage Battery storage |
75.0 MW | Agreement signed |
| Battery storage project GI-2023-178, Imperial County Battery storage |
75.0 MW | In study |
| Onshore wind project GEN-2017-105, Burt County Onshore wind |
75.0 MW | Agreement signed |
| Battery storage project AI1-130, Baltimore County Battery storage |
75.0 MW | In study |
| Solar project J1475, Clark County Solar |
75.0 MW | Agreement signed |
| Brunswick Battery Storage Battery storage · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
75.0 MW | In study |
| Cerulean Solar and Mulberry BESS Battery storage · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
75.0 MW | Agreement signed |
| Solar + storage project PIS106, Miller County Solar + storage |
75.0 MW | In study |
| Solar project GEN-2018-004, Lea County Solar |
75.0 MW | Agreement signed |
| Solar project J2068, Pierce County Solar |
75.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,857 · 519.1 GW
- ERCOT (Texas)1,986 · 447.3 GW
- MISO (Midcontinent)1,646 · 350.1 GW
- CAISO (California)429 · 188.6 GW
- Southeast (non-ISO utilities)1,067 · 161.4 GW
- SPP (Southwest Power Pool)692 · 152.4 GW
- PJM (Mid-Atlantic, Midwest)1,248 · 140.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)72 · 14.6 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)