Solar project GEN-2018-004, Lea County

Solar project GEN-2018-004, Lea County is a 75.0 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Lea County, New Mexico, connecting to SPS.

Queue statusConsented
  1. PlanningQueued Apr 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-004
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
T14 Circuit 115kV line
Location
Lea County, New Mexico
Technology
Solar: 75.0 MW
Total requested
75.0 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
26 April 2018
Proposed online date
March 2027

Location

Marker shows the centre of Lea County; the queue data does not give exact sites.