SOLAR + STORAGE · SPP

Solar + storage project ERAS-2025-020, Lea County

Solar + storage project ERAS-2025-020, Lea County is a 400 MW solar + storage request in interconnection study in the SPP interconnection queue, in Lea County, New Mexico, connecting to SPS.

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
ERAS-2025-020
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Hobbs - Yoakum 345 kV Line
Location
Lea County, New Mexico
Technology
Solar: 400 MW · Battery
Total requested
400 MW
Service type
NRIS and ERIS
Study phase
ERAS
Queue status
Active
Entered queue
2 October 2025
Proposed online date
October 2030

Location

Marker shows the centre of Lea County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Lea County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem