🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Mexico

SOLAR + STORAGE · SPP

Solar + storage project GEN-2024-124, Lea County

Solar + storage project GEN-2024-124, Lea County is a 420 MW solar + storage request in interconnection study in the SPP interconnection queue, in Lea County, New Mexico, connecting to NEETSW.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-124
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NEETSW
Connection point (POI)
Crossroads-Hobbs-Roadrunner 345 kV Line
Location
Lea County, New Mexico
Technology
Solar: 420 MW · Battery
Total requested
420 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
October 2028

Location

Marker shows the centre of Lea County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Lea County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem