United States › Grid › Interconnection queues › New Mexico
BATTERY STORAGE · SPPBattery storage project GEN-2024-SR14, Lea County
Battery storage project GEN-2024-SR14, Lea County is a 36.0 MW battery storage request with a signed interconnection agreement in the SPP interconnection queue, in Lea County, New Mexico, connecting to Xcel/SPS.
Queue statusConsented
- PlanningQueued Jul 2024 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Apr 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2024-SR14
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- Xcel/SPS
- Connection point (POI)
- Cunningham 115kV
- Location
- Lea County, New Mexico
- Technology
- Battery: 36.0 MW
- Total requested
- 36.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 8 July 2024
- Proposed online date
- April 2026
Location
Marker shows the centre of Lea County; the queue data does not give exact sites.
Power plants in New Mexico · Transmission lines in New Mexico
Other requests in Lea County
- Solar project GEN-2016-121, Lea CountySolar · 110 MW · agreement signed
- Solar project GEN-2018-004, Lea CountySolar · 75.0 MW · agreement signed
- Solar project GEN-2023-GR4, Lea CountySolar · 72.0 MW · agreement signed
- Battery storage project GEN-2018-052, Lea CountyBattery storage · 70.0 MW · agreement signed
- Solar + storage project GEN-2024-073, Lea CountySolar + storage · 500 MW · in study
- Solar + storage project GEN-2024-124, Lea CountySolar + storage · 420 MW · in study
- Solar + storage project ERAS-2025-020, Lea CountySolar + storage · 400 MW · in study
- Wind + storage project GEN-2024-278, Lea CountyWind + storage · 264 MW · in study
- Solar + storage project GEN-2024-281, Lea CountySolar + storage · 250 MW · in study
- Battery storage project GEN-2024-371, Lea CountyBattery storage · 250 MW · in study
- Onshore wind project GEN-2024-365, Lea CountyOnshore wind · 200 MW · in study
- Onshore wind project GEN-2024-366, Lea CountyOnshore wind · 200 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem