United States › Grid › Interconnection queues › Virginia
ONSHORE WIND · PJMOnshore wind project AI2-216, Pulaski County
Onshore wind project AI2-216, Pulaski County is a 77.0 MW onshore wind request in interconnection study in the PJM interconnection queue, in Pulaski County, Virginia, connecting to AEP.
Queue statusIn planning
- PlanningQueued Mar 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI2-216
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Wurno - Claytor lake 138 kV
- Location
- Pulaski County, Virginia
- Technology
- Wind: 77.0 MW
- Total requested
- 77.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 2 March 2023
- Proposed online date
- September 2028
Location
Marker shows the centre of Pulaski County; the queue data does not give exact sites.
Other requests in Pulaski County
- Pulaski SolarSolar · 150 MW · agreement signed
- Battery storage project AH1-269, Pulaski CountyBattery storage · 50.0 MW · in study
- Blue Jay SolarSolar · 100 MW · suspended
- New River Resource Authority Waste Management Facility IRD LEG-EOther · 6.0 MW · built
- Onshore wind project AC1-226, Pulaski CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project AD1-102, Pulaski CountyOnshore wind · 180 MW · withdrawn
- Onshore wind project Z2-042, Pulaski CountyOnshore wind · 180 MW · withdrawn
- Onshore wind project AC2-002, Pulaski CountyOnshore wind · 179 MW · withdrawn
- Blackbird SolarSolar · 120 MW · withdrawn
- Bella TerraSolar · 100 MW · withdrawn
- Onshore wind project W3-021, Pulaski CountyOnshore wind · 70.0 MW · withdrawn
- Solar project AC1-156, Pulaski CountySolar · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem