🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

OTHER · PJM

New River Resource Authority Waste Management Facility IRD LEG-E

New River Resource Authority Waste Management Facility IRD LEG-E is a 6.0 MW other request built and operating in the PJM interconnection queue, in Pulaski County, Virginia, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Apr 2012 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2014 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y1-049
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Wurno 34.5kV
Location
Pulaski County, Virginia
Technology
Other: 6.0 MW
Total requested
6.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
6 April 2012
Proposed online date
March 2013
Came online
December 2014

Location

Marker shows the centre of Pulaski County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Pulaski County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem