🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › South Carolina

SOLAR · SOUTHEAST

Solar project 167, Darlington County

Solar project 167, Darlington County is a 75.0 MW solar request suspended in the Southeast interconnection queue, in Darlington County, South Carolina, connecting to Santee Cooper.

Queue statusPaused / redesign
  1. PlanningQueued Oct 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
167
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Santee Cooper
Location
Darlington County, South Carolina
Technology
Solar: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Suspension
Queue status
Suspended
Entered queue
26 October 2021
Proposed online date
September 2025

Location

Marker shows the centre of Darlington County; the queue data does not give exact sites.

Power plants in South Carolina · Transmission lines in South Carolina

Other requests in Darlington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem