SOLAR · SOUTHEASTSolar project 570382, Darlington County
Solar project 570382, Darlington County is a 75.0 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Darlington County, South Carolina, connecting to Duke Energy Progress.
Queue statusConsented
- PlanningQueued Jun 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 570382
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Progress
- Connection point (POI)
- ROBINSON PLANT - FLORENCE 230KV
- Location
- Darlington County, South Carolina
- Technology
- Solar: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Other
- Study phase
- Engineering Design - In Progress
- Queue status
- Active
- Entered queue
- 29 June 2022
- Proposed online date
- February 2028
Location
Marker shows the centre of Darlington County; the queue data does not give exact sites.
Power plants in South Carolina · Transmission lines in South Carolina
Other requests in Darlington County
- Solar project 566724, Darlington CountySolar · 74.9 MW · under construction
- Solar project PP00002, Darlington CountySolar · 74.9 MW · under construction
- Solar project 566542, Darlington CountySolar · 74.9 MW · under construction
- Solar project PP00008, Darlington CountySolar · 74.9 MW · under construction
- Solar project 566518, Darlington CountySolar · 74.9 MW · under construction
- Solar project PP00009, Darlington CountySolar · 74.9 MW · under construction
- Solar project PP00001, Darlington CountySolar · 74.2 MW · under construction
- Solar project 568892, Darlington CountySolar · 76.0 MW · agreement signed
- Solar project 565080, Darlington CountySolar · 75.0 MW · agreement signed
- Solar project 566478, Darlington CountySolar · 74.9 MW · agreement signed
- Solar project PP00007, Darlington CountySolar · 75.0 MW · in study
- Solar project PP00004, Darlington CountySolar · 74.9 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem