Solar project 566478, Darlington County

Solar project 566478, Darlington County is a 74.9 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Darlington County, South Carolina, connecting to Duke Energy Progress.

Queue statusConsented
  1. PlanningQueued Jun 2022 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
566478
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Connection point (POI)
ROBINSON PLANT - FLORENCE 230KV
Location
Darlington County, South Carolina
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
Other
Study phase
Engineering Design - In Progress
Queue status
Active
Entered queue
29 June 2022
Proposed online date
December 2026

Location

Marker shows the centre of Darlington County; the queue data does not give exact sites.

Power plants in South Carolina · Transmission lines in South Carolina

Other requests in Darlington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem