United States › Grid › Interconnection queues › New Mexico

SOLAR + STORAGE · WEST

Iris Del Sol

Iris Del Sol is a 76.0 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Otero County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusConsented
  1. PlanningQueued Oct 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
IA-PNM-2020-19
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Alamogordo-Holloman Airforce 115kV line
Location
Otero County, New Mexico
Technology
Solar: 76.0 MW · Battery
Total requested
76.0 MW
Service type
Energy only (ERIS)
Study phase
LGIA executed 9/3/24.
Queue status
Active
Entered queue
15 October 2020
Proposed online date
May 2023

Location

Marker shows the centre of Otero County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Otero County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem